09.06.2023

The cost of natural gas on European hubs (Day-ahead):

TTF – 26.91 EUR/MWh ($306) (+1.6%)

THE – 27.27 EUR/MWh ($310) (+1.5%)

CEGH – 28.24 EUR/MWh ($321) (+1.3%)

PEG – 26.51 EUR/MWh ($301) (+0.8%)

The cost of natural gas on European hubs (Futures Month June):

TTF – 27.00 EUR/MWh ($307) (+2.4%)

THE – 27.67 EUR/MWh ($314) (+2.2%)

CEGH – 28.57 EUR/MWh ($325) (+2.7%)

PEG – 26.48 EUR/MWh ($301) (+2.3%)

Results of natural gas purchase from domestic production by NJSC "Naftogaz of Ukraine" :

June 2023

Volume (UGS) - 3 million cm

Weighted average price (net of VAT) - UAH 10 560 ($289)

Volume (GTS) - 5 million cm

Weighted average price (net of VAT) - UAH 10 560 ($289)

Total purchased since April 26, 2023 - 614.3 million cm

Ukrnaftoburinnya has drilled and completed gas condensate well No. 22

13/04/21

PrJSC MC Ukrnaftoburinnya (UNB) has successfully completed well No. 22 at the Sakhalin Field. Upon testing of the first target formation, a commercial inflow of gas condensate mixture was obtained with daily gas production of 280 thousand m3 and condensate of 30 tons on 9 mm choke.

The well location was initially chosen in accordance with the existing geological and hydrodynamic model, and final confirmation was obtained using petrophysical correlations based on synthetic logs.

The well depth is 4,565 meters drilled by NOV 2000 HP DC drilling rig equipped with a top drive and a triplex pumping group.

The well has been drilled and completed in 110 days (in particular, the drilling and casing period lasted for 74 days).

Ukrburservice acted as the general contractor in the drilling of the well. Products and services of Ukrainian and international companies such Spetshazbud, Burova Tekhnika, KHIM-TEKH, Dnipro Pipe Plant, Denimex, Weatherford, Schlumberger, Exalo Drilling and others were engaged in the drilling process.

“After quite difficult last year with low gas price and pandemic situation, oil and gas industry is gradually picking up with capital investments. UNB has started its drilling program on Sakhalinskoe oil and gas field, completing well No.22. Thanks to the high level of expertise and effort of geological, drilling, production, and construction departments of UNB, who were working as fully integrated team, the well was drilled with successful result. Also, we are very thankful to all contractors, which contributed into this project,” stated Miljenko Cimic, Chief Operating and Development Officer of PrJSC MC Ukrnaftoburinnya.

Source: https://unb.ua/en/news/52 

Analytics
09/06/23

Current information on natural gas prices in Ukraine and Europe ...

01/06/23

Information regarding average and weighted average prices for natural gas in Europe and Ukraine. ...

21/03/23

We have decided to dedicate this special edition to Ukraine’s gas industry and its workers who fough...

27/10/22

Presentation of the Executive Director of the Association, Artem Petrenko, during his speech at the ...

07/10/22

Presentation of the Executive Director of the Association, Artem Petrenko, during his speech at the ...